For a 3,000 sq ft custom new home in the Seattle area, full architectural services typically run $60,000 – $174,000 — about 4%–13% of construction cost. These ranges come from the Architects List cost tool, built on Seattle-Tacoma-Bellevue, WA wage data from the US Bureau of Labor Statistics and construction costs from the US Census.
| Project | Architect fee | Share of construction | Construction (est.) |
|---|---|---|---|
| New custom home, 3,000 SF | $60,000 – $174,000 | 4%–13% | $867,000 – $1,862,000 |
| Whole-house renovation, 2,000 SF | $46,000 – $145,000 | 6%–20% | $346,000 – $1,242,000 |
| Addition, 600 SF | $18,500 – $57,000 | 6%–19% | $164,000 – $466,000 |
| ADU or guest house, 700 SF | $18,500 – $55,000 | 6%–16% | $182,000 – $522,000 |
| Home size | Architect fee | Design hours (approx.) |
|---|---|---|
| 2,000 sq ft | $43,000 – $123,000 | 290–840 |
| 3,000 sq ft | $60,000 – $174,000 | 420–1180 |
| 4,500 sq ft | $85,000 – $247,000 | 590–1680 |
Implied billing rate about $146/hour. Full services = design through construction administration; consultants (structural, survey, civil, energy) are extra.
For a 3,000 sq ft custom new home in the Seattle area, full architectural services typically run $60,000 – $174,000, about 4%–13% of construction cost. A 2,000 sq ft whole-house renovation typically runs $46,000 – $145,000. An ADU or guest house of about 700 sq ft runs $18,500 – $55,000.
Most residential architects charge a percentage of construction cost, a fixed fee broken into design phases, or hourly rates for smaller or early-stage work. Smaller projects pay a higher share of construction cost because design effort does not shrink in proportion to size.
The median architect salary in the Seattle-Tacoma-Bellevue, WA area is $100,610, 1% above the national median of $99,280 (BLS). Local construction costs matter as much: new single-family homes in this part of the country run a median of about $190 per sq ft (US Census).
Consultants such as structural engineers, surveyors, civil engineers and energy modelers usually bill separately, as do permit and plan-review fees charged by the building department. Ask each architect which consultants their fee includes.
Sources: US Bureau of Labor Statistics, Occupational Employment and Wage Statistics (May 2025) for Seattle-Tacoma-Bellevue, WA; US Census Bureau, Survey of Construction. Estimates are ranges for planning, not quotes — each architect sets their own fees.